Oro Valley approves $341,000 to cover shortfall for Naranja Drive multiuse path
Summary
The Oro Valley Town Council voted 7-0 on June 30 to amend the Naranja Drive multiuse path project budget, adding $341,000 in town funds to cover a construction shortfall after bids exceeded the project estimate.
Get email alerts on the Transportation Multiuse Paths topic
No spam. Unsubscribe anytime.
Oro Valley Town Council on June 30 approved Resolution R25-34 to amend the Naranja Drive multiuse path project from La Cañada Drive to First Avenue to include $341,000 in town funding, a 7-0 vote that will keep the federal grant-funded project moving forward.
Town engineer and public works director Mr. Keesler told the council the path is a constructed 10-foot-wide multiuse path extending about 1.75 miles along the north side of Naranja Drive. Design was completed March 10, 2025, and the Arizona Department of Transportation (ADOT) — the managing agency under the intergovernmental agreement (IGA) — opened bids June 13, 2025. The apparent low acceptable construction bid, from Granite Construction, was $2,733,476; when combined with design, ADOT administration and other soft costs, the project total rose to roughly $3,999,000, leaving a shortfall of $341,000.
Keesler presented three options: have the town provide the additional funding per the IGA; rescope and rebid the project (with no guarantee of returning to budget); or cancel the project and potentially face federal reimbursement demands for work already paid for. “This project is now underfunded by $341,000,” Keesler said. He recommended the town provide the funds, noting the invoice from ADOT is dated June 25, 2025, and that the town currently has remaining fiscal year 2025 road-project savings that could cover the amount without changing the upcoming budget.
Council members had no additional questions. Mayor Winfield moved to approve Resolution R25-34 to amend the project budget to include the $341,000 town contribution; Council Member Green seconded. No public comments had been registered for the item. The motion passed unanimously, 7-0.
According to the timeline given by staff, ADOT’s board review shifted the likely construction start to mid-September 2025, with completion in March 2026. Keesler warned that canceling the project could require the town to reimburse roughly $675,000 already spent on the project. The council’s approval authorizes the amendment adding town funds so ADOT can proceed under the existing IGA.