Hartland board approves design contracts with Keller for police, administrative and fire projects after fee adjustments requested
Summary
The Village of Hartland board approved design and construction management agreements with Keller Inc. for a new police/administrative facility and a new fire station, contingent on splitting specific travel and per‑diem line items between the two contracts and circulating revised fees for final sign‑off.
Get email alerts on the Capital Projects Police Fire topic
No spam. Unsubscribe anytime.
The Village of Hartland Board of Trustees voted to approve design and construction‑management agreements with Keller Inc. for a new police and administrative facility and a new fire station, with a stipulation that several travel and per‑diem items be split 50/50 between the two contracts and returned to the board for verification before final signature.
Devin, a Keller Inc. representative, summarized the company's proposal as a two‑part engagement: design work followed by construction management, including a construction management fee pegged at about 2.5 percent of construction cost and monthly staffing charges for an estimated 15‑month construction period. "So there's 2 big portions of this. There's the design portion and then the construction," Devin said during the presentation.
The board and Keller staff spent the bulk of the discussion on how personnel and travel costs should be allocated when the village is effectively hiring the same firm to manage two concurrent projects. Trustees and staff identified four cost lines to be split between the projects: project executive travel and per‑diem, project manager travel and per‑diem, and superintendent travel and per‑diem. Keller agreed to revise the contract language and line items to reflect the 50/50 split and to deliver an updated contract document for local review before signing.
Trustee Churchill moved to approve both design/construction management agreements with Keller subject to those adjustments; Trustee Pfeiffer seconded. The clerk recorded the motion and the board carried it by voice vote.
Why it matters: the agreements set the procurement path for two capital projects that the village has prioritized after space and facility studies presented by staff. The design phase will produce plans and bid documents; only after bids are opened will the village decide whether to proceed to construction. Keller's presentation noted that if the village halted the project during design, the village would only be responsible for costs incurred to that point, not the full construction management fee.
Next steps: Keller will send a revised agreement that splits the listed travel/per‑diem items 50/50; village staff and the president will review and, if the changes match the discussion, the village will finalize signatures and proceed to bidding in the fall with a target construction start the following spring.