Council awards contracts for Yale Drive and Madison Boulevard reconstructions
Summary
The Bartlesville City Council accepted low bids for two reconstruction projects — Yale Drive and Madison Boulevard — both funded through voter-approved general obligation bond proceeds and partner contributions. Both awards were unanimous.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Bartlesville City Council on March 3 awarded two separate construction contracts to low, compliant bidders for street reconstruction projects funded in part by the city’s voter-approved 2020 general obligation bonds.
Vice Mayor Dorsey presented bid results for the Yale Drive reconstruction (bid number 2024-2025-012), describing the work as full reconstruction of Yale Drive from East Frank Phillips Boulevard to Southeast Adams Boulevard, including salvaging curb and gutter and replacing pavement with an asphalt section. Four contractors submitted, and staff recommended the low, responsive bid from KSL Dirt Works of Bartlesville for $572,306.06, which the presentation said was $223,838.94 under the remaining construction budget for that project. The council voted unanimously to accept staff’s recommendation.
Dorsey then presented bid number 2024-2025-013 for reconstruction of Madison Boulevard from Tuxedo Boulevard to the water tower. Five contractors submitted bids; staff recommended the low, compliant bid from KSL Dirt Works of $1,080,345.43. The project budget, explained during presentation, consists of the city’s portion (about $725,000) and a cost-share with the Delaware Tribe that could contribute up to $900,000; combined available funding was described as $1,450,000. The low bid was reported as $369,654.87 under the available budget. Council approved the staff recommendation by unanimous vote.
Both projects were described as part of the voter-approved 2020 GO bond program (issuances in 2022 and 2023 were cited in the presentation) and as priority projects in the city’s capital program. Staff confirmed that bid packages were publicly advertised, mandatory pre-bid meetings were held, and bids were reviewed for addenda and mathematical correctness before recommendation.
Why it matters: Both reconstruction projects are intended to bring substandard roads up to current city standards and are funded largely through previously voter-approved GO bond proceeds and partner contributions, reducing immediate general fund impact.
Votes at a glance: Yale Drive (bid 2024-2025-012) — award to KSL Dirt Works for $572,306.06; Madison Boulevard (bid 2024-2025-013) — award to KSL Dirt Works for $1,080,345.43. Both awards passed unanimously.