The board received a construction and bid schedule: bids to be advertised in March, openings in April, mobilization in late June and substantial completion by late August for several Tatum library and stadium projects; middle school auditorium and other projects have later timelines.

District staff provided a timeline for planned capital projects and the procurement schedule for several facilities upgrades, including Tatum library abatement and flooring work, stadium repairs and stormwater upgrades.

Presenters said the district will advertise for bids on March 13 and issue bid documents on March 17, receive bids on April 8 by 10:00 a.m., and award contracts on April 10. Site mobilization for the advertised work is scheduled to start on June 23, with substantial completion targeted for Aug. 29. The middle school auditorium bid process is likely two to three weeks behind that schedule, with an anticipated launch also on June 23 and an estimated completion in December 2025.

Staff said the district will follow statutory bid evaluation procedures (accepting the lowest responsible bid) and noted circumstances in which bids may be rejected, such as missing required statutory documents or bids that exceed budget; the board discussed contingency planning and the potential for re-bidding when necessary.

Ending: The board said it will review bid results and award contracts in April and monitor construction milestones for summer work that is scheduled to avoid the school year.