Folsom Streetscape project ahead but hit with utility conflicts and event sequencing that may add ~ $1.5M and two months
Summary
Public Works reported the $34.98 million Folsom Streetscape project is under construction but has encountered unrecorded utilities and major‑event rescheduling that the team preliminarily estimates may add about $1.5 million and two months to the schedule.
Project manager Carol Huang presented an update on the Folsom Streetscape Project at the Feb. 27 Public Works Commission meeting, reporting the contract award, scope, construction progress and coordination challenges.
Huang said the project was awarded on Nov. 3, 2023 at $34,979,747.50 with a construction duration of 950 calendar days and a notice to proceed issued on March 11, 2024. The corridor covers Folsom Street between Second and Eleventh Streets (about 20 blocks) and is funded primarily by SFMTA with federal, state and local funds, with SFPUC and Public Works contributing for utilities and resurfacing.
The project includes a two‑way cycle track, new medians, curb ramp upgrades, sidewalk widenings,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat