Summary

District staff told the Quarry County Board of Education that final inspections and punch-list work should finish this week and that about $48,000 in unused contingency funds will be returned to the district.

District project staff updated the Quarry County Board of Education on Feb. 25 that construction work on the middle school is in its final stages and that a final certificate of occupancy (CO) is expected once remaining paperwork is received.

The superintendent said a state building inspector signed off on key components during a Monday walkthrough and that the middle-school architect and project managers will perform a final punch-list walkthrough later in the week. The district expects to receive roughly $48,000 back from contingency funds that had been set aside for DPOs but were not used.

Staff said one emergency light issue remains; controls are expected to arrive and repairs should be completed the following day. No formal action was required of the board during the update.