Neshaminy board approves $1.12 million roof restoration for high-school gym roofs

2392303 · January 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Neshaminy Board of School Directors unanimously approved a $1,118,790.20 proposal from Tremco (Weatherproofing Technologies, Inc.) to replace roofs on High School Gym 3 and the Challenger Gym, with the district covering $291,915.20 after a facilities improvement grant.

The Neshaminy Board of School Directors on Jan. 22 approved a $1,118,790.20 proposal from Weatherproofing Technologies, Inc. (Tremco) to replace the roofs on Neshaminy High School Gym 3 and the Challenger Gym, with the board voting 9-0.

The district received a facilities improvement grant of $826,875 toward the project; by district policy the board must cover 25 percent of the grant-eligible costs, or $275,625. Board documents presented at the meeting show the contract price for the Tremco proposal would increase the district’s outlay by an additional $16,290.20, making the district’s total payment $291,915.20.

Board member Mr. Allen introduced the motion (agenda item 2.15), and it was seconded; the motion was approved by a unanimous voice vote. The resolution, as read into the record, approves the attached proposal from Weatherproofing Technologies, Inc. “subject to review and approval by the district solicitor and administration.”

District staff did not present alternate bids or a detailed project timeline during the public portion of the meeting; the motion and vote focused on approving the vendor proposal and the funding allocation. The contract award authorizes the administration to finalize the agreement after solicitor review, per the motion language recorded in the meeting minutes.

The project will affect Neshaminy High School facilities and is funded through a mix of the identified facilities improvement grant and local district funds; no additional sources or contingency amounts were specified in the board discussion.

The board’s action follows facility planning updates earlier in the meeting that included discussion of recent elementary school openings and other capital projects. The administration will return any finalized contract documents to the board and post them online as required by district procedures.