Rabbit Transit outlines $multi‑year Cameron Street headquarters, transfer center and maintenance campus

2392235 · February 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Rabbit Transit and its architects presented plans for a new campus on Cameron Street that would replace an aging maintenance facility, add an on‑site transfer center and relocate a Parks & Rec maintenance building; presenters described a three‑package construction timetable, federal grant strategy and DBE outreach.

Rabbit Transit and project consultants presented a plan to replace the agency’s 121‑year‑old maintenance and operations facility on Cameron Street with a new, secured campus that would include indoor vehicle storage, maintenance bays, a transfer center and a relocated parks maintenance building.

Presenters told Harrisburg City Council that the existing facility is dated, cramped and poses safety and operational problems. “Every system in the facility needs to be replaced,” a Rabbit Transit representative said, citing insufficient lighting, tight bus turning radii, no sprinkler system and repeated onsite collisions. Project architect Ken Anderson of Stantec described a campus design that would move bus circulation behind secure fencing, provide operator restrooms and a second‑floor training room, and accommodate future fleet transitions.

City and transit officials said the project is being advanced in three bid packages: demolition of corner parcels and Goodwill buildings (bids opening imminently), construction of a new Parks & Recreation maintenance facility (planned for fall bid), and the main transit facility (planned for a 2026 bid and two to three years of construction). Presenters said the sequence yields roughly five years of work across the three contracts and creates multiple contracting opportunities for general contractors and specialty trades.

Why it matters: presenters argued the project would reduce on‑site accidents and workers’ compensation claims, improve ADA access and transfers for riders, lower utility costs and provide a secure, modern facility for vehicle storage and maintenance. The presentation also tied the site work to local flood‑control and environmental cleanup efforts, saying the new campus would be built above the mapped floodplain and would remove underground tanks and other contaminants.

Details and funding: presenters compared utility costs at a more modern facility (about $1.15 per square foot) with the Harrisburg site (about $2.92 per square foot) and said switching toward compressed natural gas (CNG) or other next‑generation fuels could reduce operating costs; they said CNG is presently cheaper than diesel by roughly $1.60 per equivalent gallon. The team said they have applied for federal grants including the PROTECT program and plan to pursue other federal funding to reduce the local match required from state and local partners. Rabbit Transit staff said the CNG public‑private partnership is anticipated to run on the order of a decade to 15 years and that planning for a subsequent fleet transition should begin within the next 8–10 years.

Community and construction outreach: presenters committed to targeted outreach to disadvantaged business enterprises (DBE), veteran‑owned and small local contractors, and said they will host a mixer in June to connect smaller prime subcontractors with large primes. Project partners named during the presentation included PennDOT, the Paxton Creek Watershed Group, Capital Region Water, the Pennsylvania Department of General Services (which is providing parcels), and the U.S. Army Corps of Engineers (which supported floodplain/FEMA work).

Council response and next steps: council members praised the plan’s job and small‑business outreach elements and asked about transfer operations, procurement procedures (PenBid), and whether buses would be electric. Presenters said the facility will be CNG‑ready, designed to accommodate electric or hydrogen infrastructure in the future, and that service redesign and “time‑point” transfers are contingent on the new transfer center being operational. The presentation materials will be posted on the city website and updates will appear on rabbittransit.org as the project advances.

Project components mentioned in the presentation include demolition of corner parcels and Goodwill, construction of a consolidated transit operations and maintenance building, a front‑facing transfer center with operator amenities, indoor vehicle storage, fueling and wash bays, a relocated Parks & Rec maintenance facility, stormwater separation and local flood control work, and environmental remediation of former fuel/underground tank sites.