Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Town Center Planning topic
No spam. Unsubscribe anytime.
Advisory board urges town to advance town-center concept plan, flags geogrid and creek issues
Summary
Grand Island advisory board reviewed the town-center concept plan and agreed its formal role now shifts to advisory review of engineering and bids; members raised questions about geogrid costs and a downstream box culvert that may limit partial creek restoration.
Get email alerts on the Town Center Planning topic
No spam. Unsubscribe anytime.
The Grand Island Parks Advisory Board discussed next steps for the town-center concept plan, urging the town board to move the project into engineering and funding while reserving advisory review of final plans.
Members said the advisory board’s role is largely complete at the concept stage but that the board expects to review formal engineering drawings and provide last-minute input before construction funding is approved. “If it goes out to bid and they come back with engineering drawings, I would like to get that back in front of you guys,” a board member said.
Discussion centered on the scope and sequencing of work. Board members debated whether to pursue full creek restoration now or a phased approach because a downstream box culvert on Grand Island Boulevard sits about nine inches higher than the creek base and limits discharge. That culvert appears to be under New York State Department of Transportation jurisdiction, board members said, and could require DOT action before a complete restoration functions as intended.
Members weighed trade-offs on surface reinforcement for a proposed central gathering “ring.” The concept plan recommends geogrid soil stabilizer in some areas to prevent ruts and allow mixed uses; the board noted the memorandum lists a geogrid cost of about $95,000 depending on the area treated. Some members said that if the town cannot fund the whole plan at once, bids should itemize costs so the town board and taxpayers can decide which phases to prioritize.
Board members described the next steps: refine the concept plan, prepare a single comprehensive request for proposals that breaks out line items (band shell, creek restoration, lighting) and submit those to the town board to seek funding and grant opportunities. The board will expect the town to return detailed engineering drawings for advisory review before construction is authorized.