Council reviews Cedar Street reconstruction design, councilors press for traffic-calming and tree protections
Summary
The Sandpoint City Council reviewed a 60–75% design for Cedar Street reconstruction on Feb. 19 that would repave the corridor, add six-foot sidewalks on both sides, install a planter strip for stormwater and snow storage, replace an undersized water main and provide shared-lane markings (sharrows) for bicyclists.
The Sandpoint City Council reviewed a 60–75% design for Cedar Street reconstruction on Feb. 19 that would repave the corridor, add six-foot sidewalks on both sides, install a planter strip for stormwater and snow storage, replace an undersized water main and provide shared-lane markings (sharrows) for bicyclists.
Public-works staff said preliminary construction estimates were roughly $3.0 million while the city currently has about $1.9 million budgeted for the project. Staff proposed removing one block (Division to Monroe) from the scope to reduce costs and said they would complete…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat