City manager: Pecan Knoll water plant 64% complete by days; elevated tank nearing finish
Summary
City staff told council Pecan Knoll Water Plant #2 is about 64% complete by schedule and 62% complete by dollars; the adjacent elevated storage tank work is nearly finished and is expected to be filled and pressure‑tested in the coming week, with final tower completion anticipated in late March.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City Manager provided a construction and budget update on the Pecan Knoll Water Plant No. 2 and its adjacent elevated storage tank during the Feb. 18 council meeting.
Construction and schedule: Staff reported the water line connecting the plant to the main on Lou Waters Parkway is completed, site electrical and the chemical/electrical building are nearing completion, and the city is coordinating temporary startup and operations to bring the plant online before summer. The elevated storage tank (EST) is expected to be connected to the system by the week following the meeting; once connected it will be filled, sanitized and pressure tested.
Percent complete and budget: The city manager said the plant is about 64% complete by days (392 of 612 scheduled days) and about 62% complete by dollars spent. To date the city has been invoiced for approximately $8,900,000 on a project with a total budget near $14,400,000. For the elevated tank project staff said construction is about 99% complete by days and 94% complete by dollars; to date roughly $4,000,000 has been paid on a $4,200,000 approximate budget for that tower work.
Follow-up and next steps: Staff told council the city will press to get the EST filled, sanitized and pressure tested within the next week and will continue to coordinate startup testing for temporary operations ahead of full commissioning. Council asked no additional substantive policy questions and accepted the update for the record.
Quotes from the city manager: “The water line from the plant to the main on Lou Waters Parkway has been completed,” and “it is currently 64% complete based on days… and 62% complete based on dollars spent.”
What happens next: Staff will continue start-up coordination, complete final electrical and site grading work for the tank and return with any contract or budget amendments if unanticipated change orders or pay requests arrive.