City advances sidewalk program, demolition of 76 condemned homes and lead service‑line replacement projects
Summary
Public Service Committee authorized advertisement/contract actions to fund and proceed with a $1 million sidewalk replacement program, a grant‑funded demolition of 76 condemned residential structures (75% grant/25% city match), and a lead service‑line replacement program funded in part by Ohio EPA loans and grants.
Get email alerts on the Infrastructure Public Works topic
No spam. Unsubscribe anytime.
The Public Service Committee reviewed several capital and infrastructure initiatives and authorized staff to proceed with bidding, contract awards or funding steps for major public‑works programs.
Sidewalk replacement: Service Director Chris Lottó described the annual sidewalk petition program and said the committee planned another roughly $1 million in funding to continue the program. Lottó described the petition process, noted the city pays most replacement costs and homeowners are assessed at $25.25 per linear foot (approximately $125 per typical 5‑foot slab) for portions beyond program allowances. The program covers ADA ramps, some retaining walls and driveway aprons (assessed at $3 per square foot). Lottó said the funding would clear petitions submitted through July 2024 and that bids are being advertised for contractors.
Emergency demolition of condemned structures: The committee authorized using a grant from the Ohio Department of Development that covers 75 percent of the cost to demolish 76 condemned residential properties; the city will pay the 25 percent match from capital funds. Chris Lottó said three local contractors will be selected to complete the work before the grant deadline in April. Committee members asked for and Lottó agreed to provide a list of the properties to council members.
Lead service‑line replacement: The committee reviewed a mandated galvanized‑service replacement program administered through Ohio EPA/US EPA funding. Lottó said 53 percent of the funding will be forgiven by Ohio EPA; the remaining 47 percent (approximately $11 million) will be a 40‑year, 0% loan through state water infrastructure programs. The city will replace galvanized and potentially lead services under the program; Lottó said the work must be complete by 2027 and that they expect to finish ahead of schedule.
Committee members supported placing these items on the consent agenda and authorized staff to advertise and award contracts. Several members praised the programs as safety and quality‑of‑life investments and asked staff to provide lists and status updates for residents who inquire through 311.