District outlines Madison Early Childhood renovation and York vestibule security upgrades
Summary
At the Feb. 5 meeting Elmhurst SD 205 staff reviewed a major renovation plan for Madison Early Childhood Education Center and described new security vestibules, door sensors and camera installations at York High School.
Get email alerts on the Facilities Security topic
No spam. Unsubscribe anytime.
Chris Walton, district facilities staff, told the board the district is advancing a major renovation at Madison Early Childhood Education Center intended to modernize spaces for three‑ to five‑year‑old students. Walton said planned changes include a relocated main office to create a secure vestibule, conversion of the existing gymnasium into staff and conference spaces, classroom‑level bathroom access, a centralized library, larger classroom cubbies, height‑adjustable dual‑purpose furniture configured for eight learning stations, two sensory rooms, a gross‑motor space, an enlarged nurses’ office with ADA‑compliant toilet room and over 10 interior and exterior security cameras. Walton also said the project includes LED lighting with occupancy sensors and replacement of single‑pane windows.
Walton said securing York High School is a district priority and described perimeter controls that will add secure vestibules at York. He said the York vestibule will feature a pass‑through window for ID vetting, flat panels for surveillance monitoring and door‑center sensors on multiple doors (listed in the presentation). The district explained the sensors are programmed to send email (and potentially text) alerts to York staff if a door is opened or held, enabling staff to respond quickly and review video for the specific incident window.
Representatives said the Madison renovation is designed to create age‑appropriate instructional spaces and improve safety and storage; administrators did not provide a construction timetable or total project cost during the presentation. Board members asked clarifying questions about design and next steps; Walton responded on the scope of renovations and security sensor locations but did not announce funding sources or effective dates in the meeting record.