Lennar confirms elevated water storage tank location on amended plat; commissioners discuss CIP prioritization and safety data
Summary
Lennar representative said the elevated storage tank is planned at the site under review and is on the city's capital improvement plan; commissioners asked for schematics and discussed incorporating crash, fire and service‑level data into CIP prioritization.
Get email alerts on the Infrastructure Cip topic
No spam. Unsubscribe anytime.
During the Feb. 4 meeting, Mia Serrato, a representative for Lennar, told the Planning and Zoning Commission that the plot amendment reviewed by the commission includes the location for an elevated water storage tank. Serrato said Lennar has been coordinating with city staff and consultants on the tank siting and utility work.
"We have been working with Matt Richter and Cobb Finley ... to get the elevated storage tank all signed," Serrato said. She confirmed the project is included in the city's Capital Improvement Plan (CIP) and that design and plan updates were underway following recent council discussion.
Commissioners asked staff for schematics and details about the tank—s size and height; Serrato and staff said schematics and CIP materials are posted online but that some details are still being finalized. A staff comment referenced the CIP listing and a possible capacity figure discussed internally, but a confirmed storage capacity or final height was not provided at the meeting.
Commissioners also discussed CIP prioritization and whether the city solicits input from public‑safety agencies. Staff said the city engineer (identified in packet material) compiles crash and transportation data and incorporates that information when ranking street and safety projects; commissioners recommended routinely soliciting operational input from police and fire to complement data such as crash history and pavement condition assessments.
Staff noted that the city and the local Emergency Services District (ESD) coordinate on local fire‑code amendments; staff said the city generally adopts the ESD's local amendments where applicable (for example, pet boarding and sprinkler requirements), and that those amendments also factor into CIP and permitting reviews when projects involve fire‑safety infrastructure.
Why it matters: the elevated storage tank is part of the city's water‑system capital work that will influence pressure, fire flows and development capacity in the affected service area. CIP prioritization affects when streets, water and safety projects are funded and built.
Next steps: staff said they will continue coordination with Lennar and the city engineer and will update CIP materials and schematics online as they are finalized.