Turner & Townsend updated commissioners on contingency items under the project GMP, a roughly $12,000 courtroom change that will be reimbursed by the courts, and looming furniture (FF&E) orders with pricing options due this week and an ordering deadline in February.
David Mendez of Turner & Townsend told the Kootenai County Board of Commissioners on Feb. 4 that the justice building project remains within the guaranteed maximum price and that recent items are being handled through contingency rather than contract increases.
"This is all, still under the, the GMP for the project," Mendez said, adding that some contingency items moved from tentative to finalized and others remain awaiting pricing. He said an item previously thought to carry cost turned out to be no-cost and that a contractor accepted responsibility…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat