Levee project update: Army Corps work near grade, Marysville gauge active; emergency response plans in place

2175507 · January 30, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners received a status update from staff on the Army Corps flood‑protection work: most levee reaches are at design grade, an emergency action plan and material stockpiles are staged for storm response, and the Marysville river gauge remains operational while the Yuba City gauge was decommissioned in 2024.

City staff told the Marysville Levy Commission that work by the U.S. Army Corps of Engineers is nearing completion in several segments and that most of the levee is at the intended grade. Staff said the Corps’s work west of the main railroad and toward the E Street bridge is at grade, while one low area near Second Street was cut into during road‑raising work and remains a spot that would need temporary protection if water levels rise.

Commissioners were told the Corps and local partners have an emergency action plan that includes materials stockpiled to shore up small cuts if the river rises quickly. Staff said monitoring of the Marysville gauge continues; the Yuba City gauge stopped operating in January 2024 and a new upstream gauge at the Yuba City water intake structure is in service.

Staff described ongoing construction sequencing: some sections are at grade and may be two months from final grading work, subject to weather and contractor scheduling. One speaker said that if contractors need to restore the D grade, that work could be about two months away and that winter work schedules and north winds could delay short tasks by several weeks.

Commissioners and staff discussed a specific repair detail: where timber elements in steps or access areas were previously used, the contractors will replace with materials that meet current compliance requirements; staff and Corps representatives have raised the need to replace noncompliant wooden elements with concrete or other compliant materials.

Staff proposed to follow up with a short written summary from Tom (Corps contact) to the commission so members can track schedule and remaining work items. Commissioners asked staff to request that summary and to notify the commission when the final grading and associated steps work will be completed.

Ending: Staff said monitoring will continue during storm events and will be communicated to commissioners; no formal action was taken on this agenda item.