Cole County approves $67,188 change order to close out Arden Subdivision pavement project

2172156 · January 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A final change order increasing the Arden Subdivision Pavement Improvements Project by $67,187.76 was approved to cover additional curb removal, concrete approaches and subgrade stabilization discovered during construction.

Cole County commissioners approved and signed Change Order No. 1 on Jan. 28 for the Arden Subdivision Pavement Improvements Project, increasing the contract cost by $67,187.76 to close out final construction work.

Public Works staff said the contractor, TB Dozing and Excavation, encountered poor subgrade material while completing full-depth repairs and that additional payments were needed for curb removal, type-A curb and gutter, driveway approaches, bituminous paving and compacted rock used to stabilize overdug areas. Conversely, lesser-than-anticipated quantities of drain pipe, clean rock, aggregate base and full-depth pavement repairs reduced some line items. The net effect of the final adjustments was an increase of $67,187.76.

A motion to approve and sign change order number 1 was made, seconded and approved. Staff said this completes final closeout documents for the project.

Ending: County staff will finalize contract closeout paperwork and project records and proceed with any remaining warranty or administrative tasks.