Polk County solid-waste plan advances: organics and glass grants, equipment purchases and timeline

2134565 · January 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County solid-waste staff updated the board on two grant projects to improve organics and glass processing, approved purchase of a mini payloader (Ziegler) and Setco tires, and outlined an installation timeline tied to vendor proposals and grant reporting.

County solid-waste staff updated commissioners on two ongoing grant projects intended to improve processing of organics and glass and to position Polk County for upcoming extended producer responsibility (EPR) requirements. The board approved purchases of a mini payloader with a reversing fan kit and a set of solid-style Setco tires for use in glass and organics handling.

Why it matters: The equipment and contract work are tied to state and federal grant funding intended to increase the county's capacity to sort and process recyclables and organics. Staff said the projects will help capture materials (including fines, small metals and small plastics) that currently escape existing sorts and will make the facility more resilient to the packaging changes anticipated under EPR laws.

Details and timeline: Consultants and vendors (Titus and Waste Robotics) were onsite recently to verify measurements and develop a shared configuration now that the county expects to receive both grants. Solid Waste staff said Titus will produce revised drawings and budget breakdowns; updated vendor proposals were expected by month-end, with target procurement of major equipment by mid- to late February and an installation window targeted for mid-August to early September.

Procurement decisions taken at the meeting: Commissioners approved two purchases tied to the grants: (1) a mini payloader plus reversing fan kit from Ziegler and (2) a set of Setco tires for the machine. Staff noted the MPCA grant required proof of payment for reimbursements rather than invoice-only submissions, so the county will front payment and seek reimbursement per the grant process.

Operational notes: Staff described a plan to limit disruption during installation; prior MRF modifications had required only short operational interruptions. Vendors estimate three to four weeks of work for a full reconfiguration, with planned around-the-clock shifts and brief downtime windows for tying systems together. Staff also said some grant components are planning-related and will be reported separately from equipment procurements.

What comes next: Staff will return with vendor contracts and detailed cost breakdowns; the board will see contract and procurement items for approval in February. Staff will also continue work on hauling proposals and on outstanding Steam contract issues discussed in the packet.