Cedar City okays $23,119 airport change order after FAA trims scope
Summary
City council approved a revised change order for the Beryl/airport project after the Federal Aviation Administration disallowed several items; the city will cover some work from local funds and pursue operational budget or next-year capital funding for a few items.
Get email alerts on the Airport Projects topic
No spam. Unsubscribe anytime.
Cedar City Council approved a reduced change order of $23,119 for airport project AIP-049 after the Federal Aviation Administration removed or delayed several items from the contractor request.
Airport Manager Tyler Gellick told the council the FAA rejected two items and pushed one item to a later change order. Gellick said the FAA would not fund additional hallway “can lights” for the display area and would not fund a security door for the SkyWest baggage area because that door sits outside the project area. He said the city would request a private quote to add the lights and try to fund them from the airport operating budget or next year’s capital budget.
"We're requesting a quote from the company to do it outside of the project scope, and we should see that cost drop significantly," Gellick said, referring to the hallway can lights and adding the electrical infrastructure already exists.
Council members pressed whether deferring the door will increase later costs; Gellick said adding the SkyWest door later would likely be cheaper for the city because it would no longer be subject to Buy American and grant wage requirements. He said the city will seek operating- or capital-budget dollars to add the lights so the renovated terminal “looks shiny and clean” when reopened.
Separately, on a different airport contract (AIP-048) the city reported a deductive change order: the city expects a $3,540 net refund after adjustments and will invoice that through the grant. Staff said the reduction fell within the policy thresholds that allow the project manager or mayor/city manager to approve without additional council action.
Votes at a glance: Council approved change order #6 (AIP-049) as amended, for $23,119, by voice vote; Gellick said earlier FAA changes moved one item to change order 7 and excluded two items from grant funding.
Why it matters: The airport project is federally funded and subject to FAA scope and funding rules; the council's actions keep the project compliant with the grant while deciding how the city will fund non-grantable finishes.
What’s next: Staff will obtain quotes for the can lights, attempt to fit the cost into this year’s operating budget, and, if needed, include the work in the next fiscal-year capital plan.