Trustees approved an amended SVPA agreement to proceed with phase 2 of the district’s baseball/softball complex. Board discussion focused on community requests to rotate and enlarge the concession and add changing and storage space; the contract allows modest design tweaks within a 10% footprint variance.
Get email alerts on the Facilities Baseball Softball topic
No spam. Unsubscribe anytime.
The Clear Creek Amana Community School District board voted Jan. 15 to approve an amended agreement with SVPA for phase 2 of the district’s planned baseball/softball complex.
Why it matters: The project drew extended public and staff input about the orientation and interior layout of the concession and changing‑room spaces. Trustees and project staff discussed how to incorporate community suggestions while keeping the project within the design/fee parameters set by the amended agreement.
What the board approved Superintendent Dr. Seymour recommended approval of the SVPA fee amendment and the board moved and passed the agreement in a voice vote. During discussion, district staff and the architect indicated the amendment allows modest schematic revisions without a substantial fee change: the exterior footprint may vary within roughly plus or minus 10 percent while interior layouts can be reoriented to respond to user feedback. The board recorded no opposed votes.
Community input and adjustments discussed Consultants and staff summarized five primary items raised in a community field visit: rotate the concession area 180 degrees, enlarge concession square footage where feasible, add a second changing room (so both baseball and softball teams can change simultaneously), provide separate storage for equipment, and treat storage as a distinct project rather than expanding the concession’s footprint beyond budget.
Project management and schedule Architects and the district said that final change orders and pay applications will continue as the contractor works through closeout. The board was told the project can accommodate the community’s requested interior tweaks within the amendment’s parameters; more extensive redesign requiring new schematic options could trigger additional amendment work and fees.
Board action The motion to approve the SVPA amended agreement passed with a voice vote; trustees voted “aye” and no opposition was recorded.
Ending Project staff will return with design development updates per the amended schedule and the board and community can expect a subsequent presentation showing how the concession, storage and changing‑room feedback has been incorporated.