Council approves Castle Court final plat with variances; planners, developer discuss traffic and access
Summary
The Newcastle City Council approved the final plat for the 4.49-acre Castle Court development with several variances, after discussion about driveway widths, ODOT permits and on-site circulation. Planning staff and the developer described lot sizes, utilities and proposed access onto Highway 62.
Get email alerts on the Planning Development Castle Court topic
No spam. Unsubscribe anytime.
The Newcastle City Council approved the final plat for the Castle Court development, a 4.49-acre project at the southeast corner of Northeast 19th Place and North Main Street, after the council accepted recommended variances and conditions.
Planning staff told the council the site will be divided into four lots ranging from about 34,000 to 61,000 square feet within the existing CC-2 (Community Commercial) zoning and that stormwater detention will be handled in a common-area regional detention basin maintained by a property owners association. Staff said the development will connect to an existing 10-inch sanitary sewer on Main Street and an existing 8-inch water line on North Main Street.
The council and applicant debated access and traffic. Planning staff and the developer said two driveways will connect the project to Highway 62 and that ODOT permits are required. Staff described the north driveway as previously approved by ODOT and the south driveway as pending ODOT approval; the south driveway was described in the site plan as 36 feet wide with three lanes (two in, one out) while the north driveway was described as 26 feet with two lanes. The planning commission had recommended a three-lane north entrance; staff reiterated that recommendation during the meeting.
The applicant's representative said the east driveway will provide service access, delivery circulation and emergency vehicle turnaround, including a hammerhead for deliveries and trash collection, so trucks would not need to use Northeast 19th Place. The developer's representative also said the team had prepared a revised plan to show the required hammerhead and driveway radii.
Planning staff explained several variances included with the final plat: use of the existing 8-inch water line rather than the 12-inch required on section-line roads, a variance to the driveway separation measured from the Main Street intersection (the project has approximately 75 feet where 150 feet is required), and a variance to the required 200-foot separation between the project's two driveways (the plat shows about 85 feet). Staff said those variances were presented in the preliminary plat review and recommended again for approval.
Council members questioned traffic and safety at the Highway 62 access; one member said at 50 mph (possibly to become 45 mph) a three-lane entrance would reduce conflicts, and staff said the planning commission had similar concerns and had requested a three-lane design in places. After discussion, the council moved to approve the final plat as amended to reflect the agreed driveway configuration and other conditions.
The council recorded a roll-call vote approving the final plat with the recommended variances and the amendment discussed during the meeting.
The approval allows the developer to proceed with final plat recordation and to continue the ODOT permitting and coordination needed for the two Highway 62 driveways; the city will enforce stormwater maintenance through the property owners association covenants.
Background: Planning staff identified the owner as RNY LLC (Sam Patel) and the engineering firm as SRB; the applicant team attended the meeting and responded to questions about drive aisle widths, circulation, and service access.
What's next: The applicant must secure outstanding ODOT approvals for the south driveway and complete any plat recording steps required by city staff and covenants before building permits are issued.