Commission hears 2025 capital projects update: two wells, reservoir rehab and transmission work
Summary
Staff updated the commission on capital projects including two wells slated for construction, the Big Wash reservoir rehab completed in October, booster station work and progress on partner and independent transmission mains tied to the Northwest Recharge Recovery Delivery System partnership.
Oro Valley water utility staff told the commission Jan. 13 that two new wells are planned to move into construction this year and several booster and transmission projects are under way as part of ongoing capital improvements.
Lee (water utility staff) presented project‑by‑project updates. The La Posada (Nokomaskai) well—drilled earlier and resampled—was described as having specifications ready; staff said they expected approval to construct (ATC) to be issued around mid‑February so the work can be bid and a contractor selected, with the target to have the source online by the end of the utility’s fiscal year (June–July 2025) if there are no construction delays.
A second well at the Steam Pump site…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat