Staff reports 60% drawings for Cedar Street; stormwater routing to Avista property under review

2101051 · January 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the committee that 60% design drawings for the Cedar Street reconstruction are complete; changes since the 30% plans mainly address stormwater routing, including conveyance to the Avista property at the west end of Cedar Street. Sidewalks and ramps showed few design changes between 30% and 60%.

City staff told the Sandpoint Pedestrian and Bicycle Advisory Committee that 60% design drawings for the Cedar Street reconstruction were completed shortly before the Jan. 9 meeting, and that most changes between the 30% and 60% drawings relate to stormwater design.

Brandon (staff liaison) said he would distribute the 60% drawings in preparation for the committee’s next meeting. He reported that sidewalk alignment and ramp designs showed few changes between 30% and 60% materials, while the team concentrated on stormwater routing and where stormwater would discharge — notably consideration of routing stormwater to the Avista property at the west end of Cedar Street.

Staff invited committee members to review the plans and offered one-on-one meetings at City Hall with Holly (public works director) or Brandon to go over the designs. Members noted some had email-access issues and were advised plans were available in the meeting packet; staff said they would resend and post the 60% materials for review.

No formal design decisions were made at the committee meeting; staff said review and comment would continue, and that staff remain available to meet with committee members individually.