Evansville MPO staff report progress on multiple road, bridge and sidewalk projects; some lettings delayed
Summary
Staff gave a broad update on local and state transportation projects, reporting completed work on several bridge decks and pavement overlays, ongoing utility relocations and storm sewer work on Walnut Street Phase 3, and a delayed letting for the US 41 at Lynch Road intersection improvement to November 2027 due to funding.
Pam, staff member, summarized project updates for the Evansville metropolitan area, reporting construction progress, completed work and schedule changes across Indiana and Kentucky projects.
The update covered local projects including the City of Evansville Walnut Street Phase 3, where "much of the construction from US 41 to Canal Street is complete," and utility relocations and storm sewer installation continuing "from Heidelbach Avenue to Martin Luther King Junior Boulevard." Oak Hill Road work in Vanderburgh County was reported as under construction; the contractor has finished water main installation in phase 2 through William Brooks Drive and will complete…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat