City staff: HDR submitted 30% design for Big Creek Dam replacement; council to get design update this spring
Summary
City staff said engineering firm HDR submitted a 30% design package for the Big Creek Dam replacement; staff are reviewing the submittal and expect HDR to present a design update to the council later in the spring. The city directed residents to the project website for updates.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff provided a regular water-projects update and highlighted the Big Creek Dam replacement project. Derek Tokos, Community Development director, said HDR, the city's design engineer, has submitted a 30% design package and staff are currently reviewing that submittal.
Tokos said HDR is expected to present a design update to the council later this spring and that the city is maintaining a public project website at saveoursupplynewport.com for status updates and materials. Staff emphasized that water-infrastructure work is ongoing and that the council will receive the next formal update as scheduled in two months.
Why it matters: the dam and water-supply projects are critical infrastructure for municipal water supply and for local businesses and residents. The council did not take formal action at the meeting; staff signaled continuing review and forthcoming presentations from the engineering team.