Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Infrastructure topic

No spam. Unsubscribe anytime.

City staff: HDR submitted 30% design for Big Creek Dam replacement; council to get design update this spring

2218009 · February 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff said engineering firm HDR submitted a 30% design package for the Big Creek Dam replacement; staff are reviewing the submittal and expect HDR to present a design update to the council later in the spring. The city directed residents to the project website for updates.

City staff provided a regular water-projects update and highlighted the Big Creek Dam replacement project. Derek Tokos, Community Development director, said HDR, the city's design engineer, has submitted a 30% design package and staff are currently reviewing that submittal.

Tokos said HDR is expected to present a design update to the council later this spring and that the city is maintaining a public project website at saveoursupplynewport.com for status updates and materials. Staff emphasized that water-infrastructure work is ongoing and that the council will receive the next formal update as scheduled in two months.

Why it matters: the dam and water-supply projects are critical infrastructure for municipal water supply and for local businesses and residents. The council did not take formal action at the meeting; staff signaled continuing review and forthcoming presentations from the engineering team.