OpenInfra returns with phased plan to install fiber for about 600 homes in Kaufman County
Summary
OpenInfra representatives told the court they will restart fiber construction in Kaufman County in a seven‑phase rollout that connects about 600 homes; the first phase will serve 68 homes and is expected to take four to five weeks weather permitting.
Get email alerts on the Broadband topic
No spam. Unsubscribe anytime.
OpenInfra representatives on June 3 told Kaufman County commissioners they have restructured operations and are resuming a multistage fiber‑optic installation in the county, beginning with a phase that would connect about 68 homes.
Chris Harrison, representing OpenInfra, said the company has consolidated construction, operations and maintenance under one contractor, Telibor, and plans seven phases in Kaufman County that would connect roughly 600 homes over the next several months. He described phase 1 as serving about 68 homes and said the phase should take approximately four to five weeks to complete, weather permitting, with all phases running across the year for an estimated four to five months of work overall.
Local contractor Raymond of Bak Utilities will serve as the county‑based contractor managing the work, Harrison said. OpenInfra also told the court it had signed memoranda of understanding (MOUs) covering “call before you dig” procedures and committed to daily and weekly reports and to allowing county inspections and post‑installation inspections.
County staff said they had signed the MOUs and thanked the company for committing to daily and weekly reporting. Commissioners approved the fiber installation item by voice vote.
During the discussion commissioners and staff emphasized minimizing disruptions to water and other utilities and expressed support for a single, county‑based contractor model to reduce the number of different crews and subcontractors working in the right of way.
The court record does not include a roll‑call vote tally or a specific construction start date; commissioners approved the request to allow the work to proceed under the presented MOUs and routing plan.