Tipton County schools: construction of rebuilt campus progressing; roofs, brick and systems near completion
Summary
District capital-projects staff reported steady progress on the rebuilt campus: permanent power and rooftop units are being brought online, roofing is about 80% complete, brick deliveries set for later in the month, plumbing fixtures expected mid-month and several finishing trades will start soon.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Tipton County Schools’ capital-projects staff told the board the reconstruction effort on the new campus is moving into finishing trades, with roofing, mechanical work and interior finishes progressing.
Why it matters: The rebuilt campus replaces facilities damaged in a prior disaster and bringing students back to permanent buildings is a top operational priority. Construction milestones affect the district’s move-in schedule and related expenditures.
What staff reported: Mister Bennett, speaking for capital projects, said roofing was about 80% complete and that final brick deliveries were scheduled for the 23rd of the month; when that shipment arrives the contractor intended to add a brick crew to accelerate work. Permanent power is on in areas of the site and electricians are preparing to retire temporary power and connect generators. The gym finishes and hardwood flooring were described as imminent; paint crews were moving to a six-day schedule and epoxy floors and plumbing fixtures were expected to be installed later in the month. Bennett said site work on the elementary courtyard and exterior painting were underway, rooftop units (RTUs) were being set and mechanical rough-in had begun in multiple areas.
Other items: Bennett said two brick crews were working and that the contractor planned to increase crews when materials arrive. He reported that exterior drainage work and playground fall-protection spreading had been completed at some sites. The district’s project manager and trades leads were briefing staff frequently and Bennett said many workers on site are local Tipton County residents.
Next steps and timing: Capital staff said they expect to continue through interior finishes, start permanent HVAC and final electrical connections, and complete the majority of exterior brick work once the next delivery arrives. Several smaller capital projects across the district (playfield dugouts, striping, and storm-drainage work) are also nearing completion.
Ending: Board members were invited to drive by the site to observe progress; no vote or formal action was required.