School board approves $57,516 change order to replace RCEC roof and wall panels
Summary
The Vicksburg Warren School District Board approved replacing the RCEC building92s exterior wall panels and installing a new standing-seam roof after contractors found rusted panels and structural members; the work adds $57,516 to the project and will be paid from contingency funds.
Get email alerts on the Facilities Capital Projects topic
No spam. Unsubscribe anytime.
The Vicksburg Warren School District Board of Trustees voted to approve a change order of $57,516 to replace exterior metal wall panels and install a standing-seam roof at the RCEC building, the board heard at its December meeting.
District staff told the board contractors discovered rusted wall panels, corroded steel members and deteriorated purlins when they began removing the existing siding. Troy Stokes, the district92s project manager with M&P (on the line), said the contractor proposed replacing the wall panels and replacing the roof rather than applying the originally planned overlay because the existing materials were worse than expected.
Board members discussed two options: (1) replace the wall panels and install a screw-down exposed-fastener roof, which would add roughly $25,516 to the project, or (2) replace the wall panels and install a standing-seam roof, which would add $57,516. Stokes and other staff said the standing-seam product carries a longer useful life and a longer warranty than the screw-down option.
After questions about whether the roof condition was known before construction and whether purlins would be repaired, the board approved the standing-seam option and the associated wall-panel replacement. The motion passed after members voted "aye." The board noted the $57,516 will be paid from the project92s contingency fund; staff reported the RCEC project had approximately $150,000 in contingency.
The board also approved a separate motion giving Superintendent Dr. Holloway and Mr. Dodd authority to approve small change orders up to $10,000 without bringing each to the board. Board members said the smaller authorizations would allow staff to cover unplanned minor items such as electrical box replacements without repeated board action.
The board asked staff to present materials showing proposed siding colors and product samples before installation to confirm they match existing district colors.
Votes and formal action: the board approved the standing-seam change order (additional $57,516) and later approved administrative authority for change orders up to $10,000. No individual roll-call vote tally with named voters was recorded in the transcript; the motions passed by voice vote and were announced as approved.
Background: staff said the original bid called for a roof overlay and that the overlay plan was intended to cover an exposed-fastener roof. Once contractors removed siding, they found rust and deterioration that made the overlay insufficient, prompting the proposed full replacement.
The board did not set a separate project funding source beyond contingency funds and asked staff to return with any contract details and color samples before final installation.