Blaine orders street rehabilitation on Lakes Parkway; most costs to be paid with state aid and assessments
Summary
Council approved a feasibility report and project order for the 2025 Lakes Parkway and Baltimore/Davenport street rehabilitation project and authorized design and construction engineering work to proceed.
The Blaine City Council on Feb. 19 ordered final design and preparation of plans for a 2025 street rehabilitation project that includes an overlay on Lakes Parkway and pavement work on three sections of Baltimore/Davenport.
Director of Engineering Dan Schulander told council the project estimate is approximately $2.7 million; roughly $110,000 of that sum would be assessed to benefiting properties. The remaining cost is proposed to be paid from the city’s pavement management program and municipal state aid funds; some utility-related items (sanitary sewer castings and gate-valve adjustments) will be paid from public-utility funds.
Schulander said the assessment policy provides a five-year…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat