Sewer consolidation project halfway done; county reports $72M in grants and estimated household rate impact
Summary
County and consultant representatives told the legislature committees on Jan. 27 that the Elmira Sewer District consolidation project is roughly half finished, with major construction of a regional Milton Street treatment facility, conveyance pipeline and Lake Street pump upgrades under way.
County and consultant representatives told the legislature committees on Jan. 27 that the Elmira Sewer District consolidation project is roughly half finished, with major construction of a regionalized Milton Street treatment facility, a conveyance pipeline crossing the Chemung River, and Lake Street influent/pump upgrades under way.
"Program completion is slated for... we have broken this program into 3 separate contract groups," said Andrew Cuzio of Arcadis, who described completed work on site preparation and early electrical and HVAC improvements. Matt Zorro, Arcadis principal in charge, said crews have completed the moving bed biofilm reactor structural work ahead of schedule and that trickling filters and clarifiers are entering start‑up phases.
Why it matters: the project consolidates Elmira Sewer District and Sewer District 1 to meet nitrogen‑removal requirements…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat