Supervisors acknowledge addendum to conservation facility remodel; engineer recommends thicker footing and change estimated near $100,000
Summary
The board acknowledged addendum No. 1 to the conservation facility remodel; staff reported structural-engineer recommendations that add costs and bidders were notified with a 30-working-day completion clause in the bid language.
Get email alerts on the Facility Remodel topic
No spam. Unsubscribe anytime.
Worth County supervisors acknowledged addendum No. 1 for a conservation facility remodel and discussed the content and schedule implications for bidders.
County staff said a structural engineer recommended adding a thickened edge—12 to 18 inches—in front of doors rather than continuous footings, because the building is a pole-type structure and full-length footings could compromise the wall support. Staff estimated the recommended changes could add “in the neighborhood of $100,000” to the project costs. The board acknowledged addendum No. 1 by motion and voice vote.
Staff told supervisors that bid documents require contractors to complete the work within 30 working days after starting, and that the posted bid language also included an end date no later than July 31 (the transcript notes indicated some contractors asked whether that scope and timing were correct). Staff said bids were due this week and would be opened so the board could approve a bid the following Monday.
Supervisors discussed sequencing and funding, saying they preferred to have the work finished before fiscal-year deadlines and that the county would coordinate with the auditor/finance staff for necessary funds if the board awarded multiple building projects closely together.
The board approved acknowledgement of the addendum; staff will present bids to the board for formal approval at the next meeting.