DTPW interim director says parts received for Coconut Grove Metro Rail station repairs; testing and commissioning to take about 120 days
Summary
Joseph Redias, interim director of the Department of Transportation and Public Works, told trustees the Coconut Grove Metro Rail station work is underway, that required parts have arrived, and that the department expects the testing and commissioning period will take about 120 days.
A member of the trust asked for an update on repairs to the Coconut Grove Metro Rail station; Joseph Redias, interim director of the Department of Transportation and Public Works, said the department has received the necessary parts and is progressing with the work.
“...we had assurance that all the parts have been received. So all the work taking place are…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat