Fringe Road project expected to open Work Zone 1 by February; new traffic pattern in effect
Summary
Contractor aims to open the first work zone of the Fringe Road project by February. The project team implemented a modified maintenance-of-traffic plan to keep northbound traffic moving and plans phased completion through April.
Get email alerts on the Road Construction topic
No spam. Unsubscribe anytime.
Kimley-Horn project manager Gary Ritter and public information staff reported to the Town Council on Jan. 15 that the Fringe Road reconstruction project has resumed work after a holiday pause and that a revised maintenance-of-traffic plan is in effect to mitigate work-zone closures.
Ritter said contractors are focusing on bringing Work Zone 1 (from 184th down to Sterling) to substantial completion and that, because of unsuitable materials found near the Sterling/Fringe Road intersection, crews must remove and replace material before fully opening the intersection. To relieve cross-zone travel constraints, the project temporarily re-opened northbound traffic through the substantially complete portions of the work zone. The revised traffic pattern has been in place since the Monday before the Jan. 15 meeting and was distributed to schools and public-services offices.
Ritter said the contractor plans to finish Work Zone 1 by February, complete Work Zone 2 (Sterling to Tiffany) by April and then move into phase 3. Public involvement lead Janet Delgado reported steady outreach with residents and businesses, including addressing a concern by a local dry cleaner, and said the site has been maintained in a clean, safe condition over the holidays.
Why it matters: The traffic changes are intended to preserve access across the corridor while construction continues. Council members asked about traffic at Tiffany and whether additional enforcement or deployment of the town's smart radar trailers is warranted.
Key details: The reconfigured traffic plan treats Sterling Drive as local-access only while the intersection is closed to through traffic. The contractor opened northbound traffic through the substantially complete work zone to restore cross-zone connections. Staff said they will institute another maintenance-of-traffic plan when crews move from Work Zone 2 to Work Zone 3.
Next steps: Project schedule aims to open Work Zone 1 in February and move to subsequent phases; staff will continue outreach and coordinate traffic enforcement for areas with increased speeding or pinch points.
Attribution: Presentation by Gary Ritter (Kimley-Horn) and Janet Delgado (public involvement); statements reflected in the meeting transcript.