Vermillion County Commission approves $148,510 HVAC equipment purchase for Ernie Pyle building
Summary
The redevelopment commission moved to buy HVAC equipment for the county's future early childhood facility at Ernie Pyle, accepting a $148,510 sealed quote from Layton Refrigeration and discussing procurement rules, parts availability and storage.
Get email alerts on the Facility Maintenance And Procurement topic
No spam. Unsubscribe anytime.
The Vermillion County Commissioners voted to approve the purchase of HVAC equipment for the county-owned Ernie Pyle building, accepting a sealed quote of $148,510 from Layton Refrigeration for the units needed to outfit an early childhood facility.
Commissioners said the county will take ownership of the Ernie Pyle property on or about Dec. 30 and intends to adapt the site into an early childhood/daycare facility with capacity for about 156 people. Redevelopment staff reported they solicited three sealed quotes and received one response from Layton Refrigeration for American Standard equipment.
The move to buy equipment now was driven by changes in refrigerant standards and supply concerns. Presenters said industry standards are shifting away from R-410A refrigerant to newer refrigerants (discussed in the transcript as “454 b”), and suppliers warned that availability and costs for replacement refrigerants and equipment are changing. Redevelopment staff said the architect could engineer around existing R-410A equipment and that buying now could yield savings because R-410A-compatible units were still obtainable at a lower cost than then-newer systems.
Scott Craig, redevelopment attorney, described the procurement step taken: “We invited quotes from 3 suppliers under 522. We invited sealed quotes from 3 locals, and we got 1 response.” Commissioners discussed whether separating equipment purchase from later installation could conflict with procurement rules when combined project costs exceed statutory thresholds. Redevelopment staff said the purchase was for equipment only and that installation would be bid later.
Commissioners also discussed storage arrangements for the equipment on-site (the gymnasium and an on-site garage were cited as weatherproof storage options) and long-term parts availability. Redevelopment staff said suppliers and the architect expect current R-410A systems could be serviced for many years and that manufacturers would produce parts to cover warranty and repair needs for a period, though replacements or retrofits may be more costly in the long term.
A motion to approve the claim for $148,510 to Layton Refrigeration passed. The transcript records that an abstention had been recorded earlier in a related vote by Mike Hamilton because of a potential conflict of interest; the purchase motion in this meeting was approved by the commissioners present.
The county said it has appropriated funds in the economic development/redevelopment fund to cover the purchase; commissioners discussed how redevelopment and economic development budget lines and funds are organized and noted redevelopment's operating budget is limited.
The approval covers equipment only; the county indicated it will solicit installation bids when the project proceeds to that stage.