Courthouse third‑floor pour set; annex and sheriff’s remodel on schedule as county reports ARPA and construction updates
Summary
Contractor Broadus reports the courthouse third‑floor structural slab pour will commence the next morning; the annex project funded by ARPA remains under budget; sheriff’s remodel is targeting an April start and a GMP in March.
Rockwall County received construction updates at the Jan. 14 Commissioners Court meeting for three county projects: the courthouse third‑floor additions, the County Annex funded in part by American Rescue Plan Act (ARPA) monies, and the sheriff’s office remodel.
Courthouse third floor and annex (ARPA): Broadus representatives said the structural slab pour for the courthouse third‑floor project was scheduled to begin early the next morning and described no safety incidents. Project staff reported the overall annex project is on schedule and under budget; long‑lead mechanical and electrical items had been procured and were staged…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat