City engineers told the Syracuse City Council that the fire maintenance garage floor has deteriorated and is unsafe for vehicle maintenance; staff are seeking temporary space and will present options and cost estimates at a follow-up committee meeting.

Syracuse City officials notified the City Council on an emergency maintenance problem at the Syracuse Fire Department's maintenance garage, saying the garage floor has deteriorated, is unsafe for routine maintenance and cannot currently support fire apparatus.

The issue was raised during a council meeting when City Engineer Mary Robinson and other staff described inspections that found failing plumbing and an oil-water separator under the maintenance-bay floor and a subsequent depression caused when a vehicle lift was used. "We found that those systems were failing and potentially leaking contaminants underneath the garage floor," Robinson said. She added the department decided to stop parking and doing maintenance in the garage after the floor showed worsening cracking and a small pothole formed when a lift raised a truck.

The situation, officials said, leaves the department with limited options to service vehicles. "Right now, we have nowhere to fix our trucks, nowhere suitable," a council speaker said during the discussion. Staff reported a temporary agreement to use one bay at Syracuse University, but said the largest fire apparatus will not fit there. Deputy Commissioner (unnamed) summarized ongoing site searches and interdepartmental work: "After the assessment last year, Fire asked me for my help to just start looking at potential places ... to make sure that the vehicles can be, maintained appropriately and in a timely fashion." The deputy commissioner said staff have been visiting properties and expect to present several candidate locations.

Robinson described the inspection history that led to the emergency determination. City staff said the issue surfaced during a program of facility assessments; an inspection in July evaluated the plumbing and oil-water separator near the training center on State Fair Boulevard (312 State Fair Boulevard), and staff later observed that earlier cracking had progressed. Because of the risk, Robinson said staff shut down the plumbing system and the oil-water separator and are treating the facility as unfit for maintenance until more thorough engineering work is completed.

Council members and staff agreed the matter needs a formal follow-up. Councilors asked staff to prepare a memo summarizing the problem, possible short-term relocation options, and anticipated next steps. Staff said once they identify a building that meets engineering dimension requirements they will return to the council to request permission to lease or purchase or otherwise secure a temporary or permanent facility. No formal vote or appropriation was taken at the meeting.

Council discussion repeatedly emphasized that cost estimates are not yet available. Finance staff were not present at the discussion, and officials repeatedly cautioned that purchase or leasing decisions will depend on finding a suitable site and identifying funding. Michael Layman, introduced himself at the meeting as from city assessment, and asked whether the council would discuss the matter now. "Yeah. I'm Michael Layman from city assessment," he said.

The city said the garage closure has been in effect for several weeks. Officials asked the council to schedule a committee meeting to review proposed legislation or requests for authorization once staff return with site options and cost projections. In the meantime, city staff continue to inspect potential temporary locations and assess repair options for the existing garage.

Discussion points: the garage's plumbing and oil-water separator were evaluated in July; staff detected a depression in the floor after a lift raised a truck, and cracks have worsened; staff have a temporary single-bay agreement at Syracuse University that cannot accommodate the biggest apparatus; finance staff were not present and cost estimates are not yet known.

Directions given or requested: staff to prepare and distribute a memo to councilors outlining the problem, candidate temporary facilities, and next steps; schedule a committee meeting to consider specific legislation or authorization for leasing or purchase; staff to return with engineering findings and cost estimates.

Decisions and formal actions: none taken at the meeting. Staff said they will return with proposals for council consideration.

The city identified the garage as located near the training center on State Fair Boulevard and said it is continuing interdepartmental searches for a suitable temporary facility. The council set a follow-up committee meeting to consider specific actions once staff provide additional information.