Huron approves payment to sewer-lining contractor; city engineer outlines 10–20 year plan

2383252 · February 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Huron City Commission approved a $36,448.17 progress payment to HK Solutions Group for sanitary sewer lining work and heard a status update from the city engineer who said roughly half the current contract is complete and the broader city lining/replacement effort could take 10–20 years.

The City Commission of Huron on a unanimous vote approved payment request No. 9 to HK Solutions Group for $36,448.17 to continue sanitary sewer lining work.

City Engineer Brett Rungeier told commissioners the contractor is “on schedule” for the current contract and that the project is roughly 51% complete. He said cold weather recently slowed crews but that the work — televising, cleaning and lining vitrified clay pipe — is proceeding and the contractor’s current contract has a completion date of Oct. 31, 2025.

Rungeier said the lining program is long-term. “I would say 10 to 20 years yet of lining,” he said, explaining that much of Huron’s older system is vitrified clay pipe. He outlined a mix of strategies going forward: continue lining where practical to avoid street excavation, and pursue full replacement using PVC for larger-diameter runs or locations with severe deterioration.

Rungeier described the liner process to the commission as “a pipe within a pipe,” noting lining is structural and, where installed, has performed well so far. He said lining reduces infiltration and inflow — groundwater and rainwater that enter the sanitary system and increase treatment costs — and that flow monitors have shown spikes after heavy rains indicating remaining problem areas.

Commissioners asked about the timeline to complete lining citywide; Rungeier said estimates vary by condition and location but reiterated the multi-decade outlook. He added that some sections — notably the southern portion of Dakota Avenue from Ninth Street south — will be candidates for full replacement during upcoming street reconstruction in 2026–27 because of large-diameter sewers, bad manholes and significant sags in the line.

The approved payment is a routine progress payment; the staff recommendation to pay was supported by Finance Director Pauline Carey and accepted without amendment.

City staff said the lining approach has reduced the need for open-cut replacement in many locations, but replacement will be used where lining is not cost-effective or where street reconstruction requires excavation.

The commission voted to approve the payment request by roll call.