Eagan Art House, community center and Goat Hill work to finish; geothermal wells being drilled at Art House
Summary
Project staff told the Eagan Parks and Recreation Commission on Feb. 24 that interior finishing is underway at the Art House, the project’s geothermal contractor is drilling roughly 40 wells, and the community center and Goat Hill still have punch‑list items to complete before final closeout.
City project staff updated the Parks and Recreation Commission on Feb. 24 about progress at three major recreation sites: the Art House, the new community center and Goat Hill.
Tanya Mozingo and other project staff said interior finishes are in progress at the Art House, with painted walls, windows and polished concrete floors planned for public areas. Staff reported on a geothermal system under construction: contractors were drilling approximately 40 wells at the Art House site and staff said those wells are about 200 feet deep. Project staff said the geothermal field and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat