Council orders $108,000 in liquidated damages, releases $273,648.65 retainage for downtown revitalization contractor amid dispute
Summary
After receiving a presentation from MC Squared—s counsel about potential extended-cost claims, the council voted to proceed with $108,000 in liquidated damages against MC Squared and to release the contractor—s final retainage of $273,648.65, subject to a complete release of liens.
Lake Jackson City Council on Jan. 23 directed staff to assess liquidated damages of $108,000 against MC Squared and to release the contractor—s final retainage payment of $273,648.65 for work on the downtown revitalization phase 3 project.
The decision followed a presentation by MC Squared—s attorney, Adam Robertson of Andrews Myers, who urged the council not to assess liquidated damages and warned that a firm assessment could prompt litigation. Robertson told the council that MC Squared contends…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat