Nissan Stadium construction advances; DBE participation and worker-safety metrics climb
Summary
Project leaders reported construction progress on the new Nissan Stadium, including topping-out preparations, a 15-million-gallon Eastbank pump station, and rising participation by disadvantaged business enterprises and diverse workforce hires.
Project executives updating the Sports Authority on the new Nissan Stadium reported steady construction progress, rising diversity and inclusion metrics, and improving safety records.
The nut graf: contractors said the job is progressing toward a steel "topping out" scheduled for Nov. 21, with enclosure and interior work under way, while authority leaders highlighted a jump in disadvantaged business enterprise (DBE) participation and a lower-than-average total recordable incident rate.
Construction progress and milestones Calvin DeCourcy, project executive, said the site reached roughly 3.2 million labor hours and showed…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat