County project manager: Justice Center expansion within contingencies but several items pending
Summary
Turner & Townsend reported on Jan. 7 that the Justice Center expansion has used 61% of its design contingency and 29% of construction contingency; several change items remain unpriced or under review including evidence‑storage fire suppression and elevator work.
David Mendez, project manager with Turner & Townsend, gave Kootenai County commissioners a status update on the Justice Center expansion on Jan. 7. "I've distributed the update to the spreadsheet on where we stand with the contingencies for the construction of the new Justice Centre expansion," Mendez said, noting the project has used 61% of the design contingency and 29% of the construction contingency.
Mendez told the board that several of the items flagged in yellow on his spreadsheet are new and have not yet been executed. He said he expects to finalize and execute items that are…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat