Wastewater projects at Milner and Peaberg nearing system checkouts, county manager says

2303563 · January 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Routt County county manager gave a status report that Milner and Peaberg wastewater treatment plant projects have received delivered units and are progressing toward system checkouts and startup, with some remaining sludge remediation and collection‑system work.

Routt County’s county manager provided project status updates on Jan. 13 for two wastewater treatment plant projects, Milner and Peaberg. He said the treatment units were delivered some time ago and county contractors have been performing plumbing and tie‑in work.

Peaberg is scheduled for a system checkout on Jan. 31, county staff said, which will review connections and installation. The project’s next step is startup and final sludge remediation, though staff said additional work remains on the collection system. Milner is scheduled for a system checkout on Feb. 17 with a subsequent startup on Mar. 4; Milner also requires additional sludge remediation.

A commissioner asked which agency performs the final inspection. The county manager said he believed the engineer conducts the inspection and certifies it, and that the Colorado Department of Public Health and Environment (CDPHE) “has to approve the startup” but typically will not accept full responsibility for installations.

Why it matters: County wastewater plant startups involve technical inspections, contractor work and regulatory approvals; schedule shifts and remaining remediation can affect service rollout to customers.

Next steps: Staff will proceed with system checkouts and startup procedures and continue remediation work on collection systems; staff will confirm inspection and approval processes with the project engineer and CDPHE.