Developer says King's Landing PSA nearly final; site-plan reviews on schedule for September
Summary
Bill Ware, developer of King27s Landing, told the Fort Pierce commission his team expects to finalize a purchase-and-sale agreement this week and to submit final site-plan revisions by May, putting the expected city review and possible approvals on a September schedule.
Get email alerts on the Economic Development topic
No spam. Unsubscribe anytime.
Developer Bill Ware updated the City of Fort Pierce Commission on progress at the King's Landing waterfront redevelopment site, saying this week27s attorney-level edits should allow the buyer27s purchase-and-sale agreement (PSA) to be finalized and executed by the end of the week.
Ware told the commission he and the development team have completed a set of legal and design discussions and that owners and their attorneys are finishing a small number of outstanding PSA items. He said Marriott is continuing its application process for the on-site hotel; owners have asked Marriott to refresh the term sheet while final site plans are being completed.
From a schedule standpoint, Ware said the development team expects to submit final site-plan modifications by May. City staff estimated a 90-to-120-day review window once the materials were submitted, which puts a likely administrative review and potential commission action in September, Ware said. Planning Director Kev Freeman told commissioners the city is prepared to expedite pre-application meetings and suggested early coordination across departments and the FPUA to reduce review cycles.
Commissioners thanked Ware and asked staff to keep the commission informed when the PSA is executed; the record shows the commission sought a formal notice when that step is complete so the third amendment and related items could be calendared.
Why it matters: King's Landing is a large mixed-use waterfront project whose approvals and timing affect local development, incentives and downtown activity. Ware27s timeline gives a near-term target for staff and the commission to plan next steps.
What27s next: Ware indicated he will continue pre-submittal meetings with the city and submit the final site-plan package in May; staff will schedule review and next steps for the commission once that package is filed and the PSA is executed.