Contractor reports progress on Highland School project; county manager, inspector say work is on schedule and on budget
Summary
Vannoy Construction and project manager Caitlin Jones told the Macon County Board that remediation of an underground fuel oil tank is complete, 78 helical piers were installed for the middle-school addition, footings will pour the week after the meeting (weather permitting), and the project is tracking on schedule and budget.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Representatives for the Highland School project updated the Macon County Board of Commissioners on construction progress and near‑term milestones, reporting remediation milestones completed and foundation work moving into vertical construction.
Work completed and immediate milestones Caitlin Jones, project manager for Vannoy Construction, said the underground fuel oil tank beneath the planned addition has been remediated, filled with concrete and documented with the North Carolina Department of Environmental Quality. The contractor installed 78 helical piers for the middle school addition; a third‑party inspector (WSP) inspected the piers and confirmed they met design torque and intent.
Jones said footings had been excavated and, weather permitting, concrete pours were scheduled the day after the meeting and on the following Monday; steel erection is expected to start in February, with masons mobilizing at the end of the month. A vapor intrusion mitigation system was scheduled to be installed under the slab in the last week of the month so the slab could be poured and vertical work could begin.
Schedule and budget Jones told the board the contractor is ‘‘tracking on schedule’’ and ‘‘tracking on budget,’’ noting allowances are being met or come in under allowance estimates despite weather delays. County staff said they meet with the contractor twice monthly and will continue to provide quarterly updates to the board unless more frequent reporting is requested.
Speakers and oversight County Manager and commissioners praised the contractor's responsiveness and coordination with WSP (third‑party inspector) and the design team. The board and staff said the schedule is tight but achievable given ongoing weather adjustments.
Direct quote Caitlin Jones: "We are tracking on schedule. In terms of budget, we are tracking on budget and the allowances we are coming in under allowances or planning on meeting those allowances."