Sunnyvale council gets status reports on Bridal School turf, Vineyard and Jobson parks; turf choice and costs draw debate
Summary
Staff told the council the Bridal School turf field is about 95% complete and the town will cover half the cost of a new fence; Vineyard Park is roughly 10% complete; Jobson Park design is progressing toward a 60% milestone in December and a probable-cost menu is due so the council can decide what fits the budget.
Town staff briefed the Sunnyvale Town Council Monday on three parks projects—Bridal School turf, Vineyard Park and Jobson Park—and heard council and resident concerns about artificial turf, scope and costs.
Thomas Anich, presenting project updates, said the Bridal School turf project is about 95% complete and the school district will construct a perimeter fence; the town expects to pay 50% of the fence cost. “They are interested if the town council is interested, potentially hosting a ribbon cutting for this project,” Anich said. He told the council that after construction the town will perform an inspection and the school will schedule the fence work.
Vineyard Park construction is in early work, Anich said. Staff…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat