Lot 2 upgrades near completion; Colosseum Way and Windgrove utility work ongoing
Summary
Collier Engineering and fairgrounds staff reported Lot 2 retaining wall and electrical work largely complete, stormwater design revised to a sand-filter system to reduce costs, and utility relocations and potholing scheduled for the Windgrove Street intersection project.
Collier Engineering reported progress on several fairgrounds infrastructure projects, including substantial completion of the Lot 2 retaining wall, completion of an underground electrical inspection, and revised stormwater plans for the Colosseum Way realignment.
John Chaney of Collier Engineering told the board the Lot 2 retaining wall "is complete" and that "underground electrical inspection was given last week," allowing the contractor to proceed with pulling wires, setting pole bases and backfilling trenches. Chaney said underground…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat