TPWD seeks adoption of New Park Development policy setting phased timelines for opening parks

Texas Parks and Wildlife Commission · May 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission was presented a recommended policy (CPO 22) that would require TPWD to phase new park openings with public access milestones at 12, 18 and 48 months; staff recommended placing the policy on the formal agenda after public comment.

Rodney Franklin, TPWD director of state parks, presented proposed Commission Policy CPO 22 on May 21, which would require the department to adopt a phased plan for developing and opening new state parks.

Franklin described the policy’s phased approach: within the first 12 months the department would provide limited facilitated public day use (guided hunts, tours, special events) and begin initial hires; by 18 months expanded day-use access would include parking, trails, signage and restrooms; and by 48 months the department would aim to have utilities, roads and built facility infrastructure in place to support full park operations. He said TPWD would continue development beyond 48 months as needed to meet demand and conservation priorities.

Franklin said TPWD will publish detailed phase milestones and provide annual status updates to the commission and public on a dedicated website. Staff reported they had received eight public comments on the draft policy, all in favor. Staff recommended placing the item on the commission’s Thursday agenda for public comment and action.

Vice Chairman Bell and other commissioners praised the policy as a mechanism to accelerate park openings and to ensure attention to staffing and implementation. Franklin said the department has hired a centennial planner and additional staff to support early planning and expects to have a superintendent assigned soon for the Post Oak Ridge park to begin phase‑one work.

The commission did not finalize adoption during the work session; the item will return on the formal meeting agenda for public comment and action.