Gilpin County approves professional engineering contract for South Beaver Creek Road

2619804 · February 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commissioners authorized a professional consulting agreement with JR Engineering LLC for a not-to-exceed $332,590 study and project design on South Beaver Creek Road to address drainage, safety and year-round egress concerns.

The Gilpin County Board of County Commissioners voted 3-0 on Feb. 11 to authorize a professional consulting agreement with JR Engineering LLC to complete engineering services for South Beaver Creek Road.

Public Works Director John Combs and a JR Engineering representative described options the county had received: a larger, grant-ready engineering package quoted at about $553,408 and a reduced scope that would provide corridor surveying, geotechnical investigation, drainage improvements, core samples and intermediate recommendations at a lower cost. Based on uncertain federal grant prospects, staff recommended the smaller, less costly option and confirmed a contract not to exceed $332,590.

John Combs said the contract would include core sampling (19-21 bores were referenced in the proposal) and a design package that could be used either to phase local work or to make the project eligible for future grants. "Those core samples alone are gonna be very helpful," a JR Engineering representative said about informing material and topography decisions.

Commissioners and staff discussed whether a Conditional Letter of Map Revision (CLOMAR) would be necessary if the roadway elevation were altered, noting CLOMAR is a FEMA process that can add about a year to project timing and may require coordination with the U.S. Army Corps of Engineers. JR Engineering advised that an optional CLOMAR/permit scope be included because of the road's proximity to the creek.

The board voted to adopt resolution 25-14, authorizing execution of the agreement with JR Engineering LLC, with the contract capped at $332,590. The county said public outreach steps will include at least one open house in spring and later public meetings around 70% design.