City presents Mustang Park multigenerational center plan, sets GMP at roughly $80 million and 2027 completion target
Summary
City staff described the Mustang Park Multigenerational Center and indoor aquatic facility plan and said a construction-management amendment would establish an initial guaranteed maximum price (GMP) of about $80 million and a substantial completion date in May 2027.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Trevor Crane, director of capital improvement programs, presented the Mustang Park Multigenerational Center and indoor aquatic facility concept and schedule to the Irving City Council.
Crane said the project is part of the city’s Let's Play Irving Aquatic and Community Center initiative. The proposed facility would be about 127,000 square feet and include common areas, program spaces, athletics and fitness space, a dedicated senior area and indoor aquatics. "This amendment will set the initial guaranteed maximum price of just over $80,000,000," Crane said, and he provided a target substantial-completion date of May 12, 2027.
Crane described renderings and program elements, including a walking track, children’s activity areas, a senior entrance and multiuse spaces. He said the city expects a groundbreaking in late June or early July 2025 and an estimated opening in June 2027.
Why it matters: The center would add substantial indoor recreation and aquatics capacity for Irving residents and represents a major capital project with a multiyear construction schedule and a guaranteed maximum price that will affect budgeting and cash-flow planning.
Status: City staff presented the contract amendment and GMP to council during the work session. The transcript records staff presentation and council questions; a formal vote or ordinance text establishing the GMP is not recorded in the meeting transcript included here.