Garden Grove council hears construction, schedule and park design update for Civic Center Revitalization project
Summary
City and development partner Edgemoor reported construction progress on the new public safety building and presented designs and programming plans for a future Civic Center park. Officials said the building foundation will be finished soon and the park construction documents are expected in March 2025.
Get email alerts on the Civic Center Revitalization topic
No spam. Unsubscribe anytime.
Garden Grove city officials and their development partner gave the council a progress report on the Civic Center Revitalization Project, detailing work on the new public safety building, construction milestones and the conceptual design for the Civic Center park.
The update matters because the project replaces the existing police headquarters, relocates the police memorial, adds conference and community spaces and will create a new park intended to knit the civic campus — police, library, senior center and city hall — together.
Edgemoor and city staff said the project has moved rapidly: site-preparation and stone-column installation to improve soils are complete, the foundation work is expected to be finished imminently and the police building has begun to rise. Project leaders outlined a construction schedule that aims for structural topping out later in 2025 and a watertight building by late 2025, followed by parking garage work and, ultimately, construction of the park after the police department relocates.
Edgemoor representative Christina Solomon described the public safety building as a new police facility at Euclid and Acacia that includes a publicly visible “beacon stair” and a ribbon-like architectural element leading to a second-floor briefing room overlooking the relocated police memorial. Christina Solomon said the design balances visibility and security: glass will admit light while selected glazing limits direct sightlines into secure areas.
Construction lead Keith (surname not specified in the transcript) described substantive recent work: hundreds of stone columns installed 20 feet below the surface to improve load-bearing soils, ongoing large concrete pours for slab-on-grade and elevated decks, and below-grade utility connections on Euclid and Acacia. He told the council the team expects to complete below-grade utilities in February and to top out the building in the months that follow.
Project managers also presented the park concept, describing an event lawn sized for multiple programming scenarios, a stage, a playground and fitness nodes, walking routes that link city hall to the senior center, a quieter Memorial Grove, a restroom building, repurposed public art from the existing park and a ‘‘green corridor’’ connecting the police building to the library. The design includes lighting studies to make the green corridor feel safe at night and a proposed landmark/plaza that will terminate Civic Center Drive.
Staff said construction documents for the park are expected to be complete by March 2025 and that the park design work is nearly finished. They described programming capacity on the event lawn (examples shown by staff: seated events for roughly 2,500 people, concerts for about 2,000 people, movies/yoga for about 500, and space for approximately 14 food trucks around perimeter paths) as planning inputs for future operational decisions.
Council members asked several operational questions and offered feedback. Mayor Pro Tem Joe Dovin, Councilmember Breidingham and others praised the pace of progress; Breidingham offered to donate cherry trees for the new park. Council discussion raised community concerns previously expressed about a former park lake; staff said they are studying options and costs for a water feature and will report back. Staff emphasized that any decision on substantial features will include cost and maintenance considerations.
City staff declined to provide a binding timetable for park programming rules and hours beyond noting that the city’s municipal code sets standard park hours unless the council adopts a different ordinance. Staff also said the park stage is intended to be available for use when not reserved for events, with some times restricted for programming.
The presentation concluded without a council vote. Staff and the development team said they will return with subsequent project milestones and invited council and public engagement as plan-check and construction phases continue.